Pubic police inspection NO.065258
INSPECTION REPORT
Product name: riot suit
Specification of the type: FBF-S
Inspection category: model inspection
Report date: October 20th 2006
Ministry of public security special police equipment quality supervision inspection center
Public police inspection NO.065258 total page: 6 no. 1
|
Product name and type |
FBF-S riot suit |
|
Sampling date |
October 16th 2006 |
Sampling place |
factory |
|
Base number |
600 sets |
Sample quantity |
2 sets |
|
Batch number |
06-01 |
checker |
Wang Lizhu |
|
Inspection base |
GA- 422-2003 riot suits |
|
N/A |
|
Inspection date |
October 18th 2006 ¨C October 20th 2006 |
|
Inspection conclusion |
Through inspection the sample of FBF-S riot suits .The inspection conclusion was fulfill the stipulated with <<GA 422-2003 riot police shield>>. |
Public police inspection NO.065258 total page:6 no.2
|
Inspection place Inspection environment Inspection equipment |
|
Inspection place (include items and sport check ) |
Ministry of security special police equipment quality supervision inspection center |
|
N/A |
|
Inspection environment (special environment demands) |
Indoor: temperature 25* C humidity 40%RH atmospheric pressure 1005hPa |
|
N/A |
|
Main inspection equipment |
Domestic general standard measure
Domestic common hand machine
American INSTRON 4204 pull testing machine
Domestic drop hammer impact testing machine
Domestic electronic weigh
Domestic high -temperature text chamber
Domestic low-temperature text chamber
Domestic level upright burning tester
Domestic oxygen instrument
|
|
Describe of inspection samples |
Riot suit consist of chest, abdomen,, crotch, upper limbs, lower limbs and so on protect parts. Prothorax use thick foam 1.5mm, 1mm pc ban, 4mm foam loyer2, 2mm thick aluminum sheet overlapping, 2mm felt, back use 4mm foam loyer2 molding, 2mm aluminum sheet overlapping, foam and so on ; limb protection course use molding armor and soft absorb energy material .
|
Public police inspection NO.065258 total page: 6 no.3
|
Inspection items Inspection results |
|
Serial number |
Inspection items |
Technical(standard) demand |
Sample number |
Inspection result |
judgment |
|
1 |
Outline inspection |
Riot suit have no gauffer, rift, dilapidation, gap, unstitch, drop needle, thrum and so on |
NO.1-NO.4 |
Meat demand |
P |
|
2 |
Quality inspection |
Riot suits total qualities are not less than 8.5kg |
NO.1 |
6.5kg |
P |
|
3 |
Dress flexibility inspection |
It must be dress flexibility, easy to get of ,it can not obvious limited arms free motion and genuflect, jump, squat, run, pitching, swivel |
NO.1 |
Meat demand |
P |
|
4 |
Protect area inspection |
chest, abdomen,, crotch, |
Large-size : >0.26sq.m
|
NO.1 |
Meat demand |
P |
|
Back |
Large-size : >0.14sq.m |
|
upper limbs |
Large-size : >0.26sq.m |
|
lower limbs |
Large-size : >0.42sq.m |
|
5 |
Structure connect strength inspection |
Button strength : >300N
Nylon fibulae : >120N
Connective band mightiness : >2200N
Other parts connect strength : >250N |
NO.1 |
Give the stipulated force value on the connecting fitting ,all can meat demand |
P |
|
6 |
Prevent thorn performance inspection |
Use standard text cutter for prothorax, back, abdomen, crotch, 20J kinetic energy, upright pierce into armor coat, knifepoint can not through armor coat |
NO.1 |
Meat demand |
P |
|
P=pass F=fail N=un-inspection A=allow |
Public police inspection NO.065258 total page: 6 no.4
|
Inspection items Inspection results |
|
Serial number |
Inspection items |
Technical(standard) demand |
Sample number |
Inspection result |
judgment |
|
7 |
Shockproof performance inspection |
Put any protect parts of the suit on the face of rigidity use 20J kinetic energy the parts will not dilapidation craze |
NO.1 |
Meat demand |
P |
|
8 |
Impact energy absorb performance inspection |
Lay the prothorax back parts of the suit on the standard plaster, use 100J kinetic energy the deep of plaster impress can not exceed 20mm |
NO.1 |
Meat demand |
P |
|
9 |
High-temperature prevent thorn inspection |
Let riot suit put into +55*C+2*C thermo tank keep it for 4h, then going on prevent text, the result must be demand the request of prevent performance |
NO.2 |
Meat demand |
P |
|
10 |
High-temperature shockproof performance inspection |
Let riot suit put into +55*C+2*C thermo tank keep it for 4h, then going on shockproof text, the result must be demand the request of shockproof performance |
NO.2 |
Meat demand |
P |
|
P=pass F=fail N= un-inspection A=allow
|
Public police inspection NO.065258 total page: 6 no.5
|
Inspection items Inspection results |
|
Serial number |
Inspection items |
Technical(standard) demand |
Sample number |
Inspection result |
judgment |
|
11 |
low-temperature prevent thorn inspection |
Let riot suit put into -20*C+2*C thermo tank keep it for 4h, then going on prevent text, the result must be demand the request of prevent performance |
NO.2 |
Meat demand |
P |
|
12 |
low-temperature shockproof performance inspection |
Let riot suit put into -20*C+2*C thermo tank keep it for 4h, then going on shockproof text, the result must be demand the request of shockproof performance |
NO.2 |
Meat demand |
P |
|
13 |
Protection course fire resistance property inspection |
Use Bunsen burner going on resistance text of protection course, let luminous tube and sample became 45* corner, the distance of luminous tube top and sample is 10mm, control high of the Bunsen burner blue flame is 20+2mm,move the Bunsen burner when fire 10 minutes, sample burning time will not exceed 10s |
NO.1 |
Meat demand |
P |
|
P=pass F=fail N= un-inspection A=allow
|
Public police inspection NO.065258 total page: 6 no.6
|
Inspection items Inspection results |
|
Serial number |
Inspection items |
Technical(standard) demand |
Sample number |
Inspection result |
judgment |
|
14 |
Surface course oxygen index inspection |
According to the standard stipulated ,surface course oxygen index can not less than 28%,contral the flow of oxygen is 3.19L/min, the flow of alkaline air is 8.21L/min: damping the sample 58x150mm then fixed in the specimen holder, ignite the sample ,burning time must central in 10-15s ,move the ignite ,write down the continue burning and smolder, in 2 min continue burning and smolder mar length can not exceed 40mm |
NO.1 |
Meat demand |
P |
|
P=pass F=fail N= un-inspection A=allow
| |